The club expect to generate an additional £28m a year from match days at the new stadium, a rise of more than 50 per cent, with the majority coming from the additional corporate hospitality facilities in the new stadium.
Makes no difference to tebbout turned cost in £££ at this stage though
It’s just a flimflam article IMO
For a. 25% uplift at this point you would only maybe (and I mean maybe) see that in acceleration costs and we would look at that vs the cost of Wembley and just stay there another year putting this into a job on days
I’m sure it will have been financed on 24 hours working so it just smells of complete bull
Is it just me or does that read as
"!"£$%^&*()_OIUHGFDSW£$%^&*(O)(*^£"!!"£^&*()__$WERTYUIJHGFD$£_£"£$%^&*())&"£$%^&*()_OI£$%^&()££$*()OIHGFDFRE£$%)FGHJ" ?
As painful as much news is (if true), you might wanna read this report on the London Stadium (scroll down to table).
http://www.skyscrapercity.com/showthread.php?t=610996&page=886
When are those fudging idiot newspapers, who's job are to dig up facts, going to stop using the 10 year old scrapped design in their articles? It's incredible what a brick job they do!! How are anyone gonna believe a word, when they can't even get the simplest of facts right!
I'm talking about them using pictures of the original KSS design from 2007! It's 5 years since Populous took over and presented the current design, which looks nothing like the one they have pictured.Having worked in the media for my entire career I can say I never met a journalist who could add up or understand figures and that included their expenses!
I'm talking about them using pictures of the original KSS design from 2007! It's 5 years since Populous took over and presented the current design, which looks nothing like the one they have pictured.
Basically there is no way we wouldn’t have costed for 24 hour shifts with the plan we had
Materials have gone up but around 6%
So how on earth could we have a 25% increase on what was already a premium build....
The only thing could be asking them to do more in less time (acceleration) but again I thought that was all in the programme
That thing on the ground is massive.
I don't understand this comment. Why would cost acceleration be in the baseline programme? There might be a provision within the contingency pot that forms part of the Anticipated Final Cost figure but this would most likely not fully cover the cost of programme acceleration since it would be calculated by probability across a range of values.Basically there is no way we wouldn’t have costed for 24 hour shifts with the plan we had
Materials have gone up but around 6%
So how on earth could we have a 25% increase on what was already a premium build....
The only thing could be asking them to do more in less time (acceleration) but again I thought that was all in the programme
I don't understand this comment. Why would cost acceleration be in the baseline programme? There might be a provision within the contingency pot that forms part of the Anticipated Final Cost figure but this would most likely not fully cover the cost of programme acceleration since it would be calculated by probability across a range of values.
Equally you wouldn't include programme acceleration in your baseline programme, but if the need is identified through review of project progress towards milestones then the programme would be rebaselined with programme acceleration costs built in...unless you are saying that has already happened?
I don't understand this comment. Why would cost acceleration be in the baseline programme? There might be a provision within the contingency pot that forms part of the Anticipated Final Cost figure but this would most likely not fully cover the cost of programme acceleration since it would be calculated by probability across a range of values.
Equally you wouldn't include programme acceleration in your baseline programme, but if the need is identified through review of project progress towards milestones then the programme would be rebaselined with programme acceleration costs built in...unless you are saying that has already happened?
Are these costs limited to the stadium or is it the whole NDP project?