I keep on saying it..... but I don't think there is that much to do.So do you all think we now have 3 full months to complete the stadium? East side looks quite a bit off as does the South exterior. GHod knows what the interior looks like.
I think that the thing we miss (unless we are involved in the trade) is that on building projects this scale some interior fit outs will be completed way before exterior work is done. We completed a fairly significant build last year, and I couldn't believe when touring in hard-hats, high viz etc. as heavy work was still taking place in one area, that just round the corner the changing facilities and showers were complete, tiled and looked ready to use.So do you all think we now have 3 full months to complete the stadium? East side looks quite a bit off as does the South exterior. GHod knows what the interior looks like.
I don't know how to use the like button.i’ve no idea why there is such time negativity towards this, looks like it’s being thrown up to me. With 3 months to go I see no reason why it wouldn’t be ready if it continues at the current pace.
I keep on saying it..... but I don't think there is that much to do.
East stand is just the facade
South stand is just the glazing.
Interior fit outs tend to take very little time.
My big worries until recently were the roof (which seems to have sped up significantly in the past week or so) and the sliding pitch (that was successfully tested last week).
From who?!?Heard it wasn't going to be ready, but the NFL have insisted it must be. So now we're throwing money at it.
I keep on saying it..... but I don't think there is that much to do.
East stand is just the facade
South stand is just the glazing.
Interior fit outs tend to take very little time.
My big worries until recently were the roof (which seems to have sped up significantly in the past week or so) and the sliding pitch (that was successfully tested last week).
Various people working on the build there that I know.From who?!?
I was speaking to one of the crane drivers at a party on Sunday and he said they're 6 weeks behind. He thinks that's the max it will be though so not too outrageous. On a side note, the green crane that can be seen sitting where the pitch will be is costing £6k per day to hire. Not bad work if you can get it!