Really lifts haven't been cabled yet? Doesn't sound right surely.
He's made some additional replies to different people in various places:
Hi Paul, once the fire system and PAVA is linked and on test, then I will be able to say when. I posted a while back that if the system is not under test by the 1st week of Nov the commissioning team will struggle to get it signed off in time. Dec sign off is doable but loads risk involved. So many zones to get checked, and then get the SMS integrated which the CCTV, PAVA, Fire, Radio, CIS & lifts etc.
Only the fire alarm cabling to my knowledge but I would also think some of the PAVA cabling has been damaged as well...lift cabling is not in atm well done at the shaft demarcation point.
Yes mate defo a pic from yesterday, the scaffold and seats are not the issues with the stadium. This will all be done alongside the pitch in Nov. It's the PAVA, fire, lifts, SMS, CCTV & radio testing/commissioning that is the real problem...
All the cabling faults are being rectified, and last remaining cable installs are being pulled currently. I will stand with my tweet from a while back that the zone testing will start in Nov. If okay then 6 weeks the Commissioning should be done, then sign off.
If these critical tests fail then we will not get into the stadium until next season. The club will not be able to tell us anything until the above tests are done. Once the testing is underway, I will be able to advise. If a fire alarm is activated it will then trigger the PAVA to go off after a set time, which will evacuate the stadium. Radio is also critical, and I would think the stadium may have mist suppression installed. I will try and find out.